Almost exactly one year after we moved onto our plot, we could finally get on with casting the concrete footings. We were very excited! I keep on going outside to admire Louis’ handiwork because this really is a big deal. Our future house will be standing on those very blocks of concrete. All this hard work, that is now behind us, will keep our house straight and secure. Even though they will soon be buried under dirt and the shipping containers, this is what will support the weight of the house above.
Louis and his team managed to cast all twelve of the concrete footings in one week. Disappointingly, the concrete mixer has turned out to be one of those glitchy things that will only work for one person (seemingly Kevin who was not on site). Therefore, the concrete had to be mixed by hand. Not ideal, but doable.
For every bag of concrete, we used a wheelbarrow of sand and two wheelbarrows of stone, along with the necessary water. To cast the footings, we used over twenty bags of cement. Louis did not follow the formula as written on the bags of concrete, but rather chose to use a formula that will guarantee a slightly harder result. This will allow us to position the shipping containers a little quicker as the concrete will be able to carry the weight sooner.
This is how Louis went about casting the concrete footings:
Casting Concrete Footings
Step 1
The footings each have a pin sticking out the top. These pins will be used to anchor the shipping containers to the footings. The pins, which are made from threaded rod, are tied to rebar which is embedded deep into the concrete. Should a tornado ever hit the Western Cape, and the house tries to fly away, the concrete blocks should keep the house tied to the ground. The rebar embedded in the concrete should stop the pins from tearing out of the blocks.
Some of the footings have two pins standing out the top. This is where the two corners from two shipping containers will meet and sit together on the same footing. There are a total of twelve footings, and four of the footings have two pins.
Step 2
We then filled the base section with concrete. After every few shovels of concrete mixture, the team shook the box around to get rid of any air bubbles because air bubbles would result in weak areas. They only added more concrete when they were satisfied that all the air bubbles had been removed.
Step 3 & 4
We attached the rest of the wooden box mould to the base. As you can see, this was in a slightly pyramid shape. Louis and the team then filled it up in the same manner as the base. Once again the guys made sure to shake it around every few shovels to reduce the chance of air pockets.
Step 5 & 6
Louis then added a small cap mould and cast that. He removed the wooden box mould only when the concrete had cured. And, voila… we had a concrete footing. Louis could then reassemble the wooden pieces for the next casting.
Input from the Structural Engineer
We had to cast the footings in accordance with the specifications supplied by John Moll, of GM Civil Engineers, our structural engineer. We had two sizes of block base to cast. The single-storey section of the house needs to have a base area of 700mm x 700mm x 250mm, and the double-storey section of the house needs to have a base of 900mm x 900mm x 250mm.
We also had to cast the concrete to the correct MPa rating (hardness), or harder. We have cast a smaller block of concrete for testing. It can be sent away for testing, should it be required by the engineer.
Moving the Footings Into Their Final Position
There was one more thing to do after all the footings were cast, cured and unboxed. We got out the laser measure and measured the distance between all the pins. The pins need to be in the right place, with a only small margin of error allowed, so that the shipping containers can just slot on to them. About four of the footings needed to be moved a few centimeters until they were in the correct place.
We did this by placing wooden boards against the side of the hole, then between the wood and the footing we placed a hydraulic jack. Slowly we used the jack to push the block into place. It worked very well!
One last small note for those of you following our project. Last week’s site inspection went very well. The inspector was only there for about fifteen minutes, but she’s happy with progress and gave us her blessings to continue. Yay!
The jack is such a good idea!
I agree! I don’t think I would have ever thought of it. I would probably have just stared at this huge block in horror when faced with the task of moving it. Louis estimates a footing’s weight to be close to a tonne, and there’s the friction from the stones underneath to consider too.
This is a particularly exciting post. I think this is the first step in the project that is not just laying the groundwork but constructing the house itself, isn’t it? It must have been anxiety-inducing building a component that is so important to keeping the house safe but with such a small margin of error! Well done to everyone involved.
Also, congratulations on getting the site inspector’s approval to continue!
That is exactly how I see it too. This is where the actual house itself begins! I will be happier when the containers in place.
It is so exciting to see construction on your actual home begin at last. Yayy! Cannot wait to see how it progresses hereon out
Thank you – we’re looking forward to good progress from here on. 🙂
Thank you for sharing your journey in building your container house project. I like your content and I really gathered a lot of new information and knowledge. I am excited to learn more tips on how you’ll build your container house.
Thank you for your kind words!